Electrical Cheat Sheet
Electrical Cheat Sheet
1. Ohm's Law
V = I × R
2. Power
P = V × I
P = I² × R
P = V² / R
3. Energy Consumption
E = P × t
4. Series Circuits
R_total = R1 + R2 + R3 + ...
5. Parallel Circuits
1/R_total = 1/R1 + 1/R2 + 1/R3 + ...
6. Voltage Division (Series)
Vx = (R_x / R_total) × V_total
7. Current Division (Parallel)
Ix = (R_total / R_x) × I_total
8. AC Formulas
V_RMS = V_peak / √2
I_RMS = I_peak / √2
9. Power Factor
PF = cos(ϕ) where ϕ is the phase angle
10. Reactance and Impedance
X_L = 2πfL (Inductive Reactance)
X_C = 1/(2πfC) (Capacitive Reactance)
Z = √(R² + (X_L - X_C)²)
Remember: Always check units and safety factors while designing circuits.
Power Design Guide
Initial Steps Before Low Voltage Power Design
Coordinate with state, local, and city ordinances
Either with outside consultant OR proceed with internal design
Initial Demand Load Estimating
Need SQ Estimates from Architectural Divisions before continuing
Review NFPA 70 - Article 230 for assistance
Load Estimating Reference
| Load Type | NFPA 70 Reference | Notes |
|---|---|---|
| Receptacle Loads | 220.14, 220.80 | ~180VA for each receptacle |
| Lighting Loads | 220.12, 220.80 | |
| HVAC Loads | 220.61, 440 | |
| EV Charging | 625 | |
| Equipment Loads | 220.42 | |
| Outside Branch Circuits | 225 | Site Lighting (225.25), EMG/Fire Pumps (225.30 A) |
Demand Load Calculator
Service Size Estimating
Ensure proper spare capacity has been accounted for - NFPA 70 Article 220.56
Standard Service Sizes
Common service sizes: 100A, 200A, 400A, 600A, 800A, 1000A, 1200A, 1600A, 2000A, 2500A, 3000A, 4000A
One-Line Programming
Key Considerations
- Determine if service is greater or less than 1200A
Typical cutoff for Switchboard vs. Distribution Main Panelboard
- Determine Customer/Project metering requirements
Ensure all loads are properly segregated and assigned metering
Panelboard Sizing Reference
| Branch Load Type | NFPA 70 Reference |
|---|---|
| HVAC | Articles 440 and 220 |
| Lighting | Article 210 |
| Receptacles | Article 210 |
| Emergency | Articles 700 and 701 |
Panel Configuration
- Determine if panels are to be MCB or MLO
- Size MCB accordingly - NFPA 70 Article 240 (OCP)
Conductor Sizing
- Consider AL or CU conductor type
- Determine conductor sizing from estimated load
- Determine estimated run length
- Determine voltage drop and potential upsizing - NFPA 70 Article 220.55
- Determine conduit size - NFPA 70 Annex C
Must be below 30% fill rate
Microgrid Strategies
| Strategy | NFPA 70 Reference |
|---|---|
| BESS (Battery Energy Storage System) | Article 706 |
| On-Site Generation | Article 705 |
| External Microgrid Feed Paralleling Utility | Article 705 |
| Utility Back-Feed | Article 702 |
Initial Power Layout - SD
Electrical Room Requirements
| Requirement | NFPA 70 Reference |
|---|---|
| Working clearances | Article 110.26 |
| Door/Exit requirements | Article 314.20 |
| Installation requirements | Articles 300, 430 |
| Disconnecting means requirements | Article 225.30 |
Consider distance to sources of branch circuits when determining locations
Initial Layout Checklist
Overhead Doors, HVAC, Process Mechanical, Fire Smoke Dampeners, Actuators, Unit Heaters, Make Up Air Units, Condensing units, Pumps, etc.
Receptacle Placement Guidelines
- Typically mounted at 18" afg - NFPA 70 Article 210.52(A)(1)
- Typically no longer than 6' away from desired use/appliance - NFPA 70 Article 210.52(A)(1)
- Determine receptacle use for tables/counters
- Determine if space requires GFCI receptacles - NFPA 70 Article 210.8(B)
- Determine if space requires floor box receptacle installations - NFPA 70 Article 210.52(A)(3)
Load Estimator
Project Information
Lighting Loads
General Lighting Load by Occupancy - NEC 2020 Table 220.12
| Type of Occupancy | Unit Load (VA/sq ft) |
|---|---|
| Office Buildings | 1.30 |
| Parking Garage | 0.30 |
| Transportation | 1.20 |
| Warehouses (storage) | 1.25 |
| Schools | 3.00 |
Receptacle Loads
Typically 1.0 VA/sq ft for office spaces
HVAC & Major Equipment Loads
Summary of Demand Loads
| Load Category | Connected Load (kVA) | Demand Factor (%) | Demand Load (kVA) |
|---|---|---|---|
| Lighting | 0.0 | 100 | 0.0 |
| Receptacles | 0.0 | 100 | 0.0 |
| HVAC & Equipment | 0.0 | - | 0.0 |
| Total Demand Load | 0.0 | - | 0.0 |
Ohm's Law Calculator
V = I × R | I = V / R | R = V / I
Power Calculator
Single Phase: P = V × I | Three Phase: P = √3 × V × I
HP Conversion
Conversion Factors:
• Mechanical HP: 1 HP = 745.7 W
• Electrical HP: 1 HP = 746.0 W
• Metric HP: 1 HP = 735.5 W
Voltage Drop Calculator
| Wire Size | Vd (V) | % Vd |
|---|
Pull/Handhole Box Sizing (Large)
Results
Small Junction Box Sizing
Results
Conductor Sizing/Ampacity Calculator
Internal Conductor Sizing
Standard Sizing Reference
| Amp Range | Phase Conductor | Equip Ground | Conduit |
|---|---|---|---|
| 15-20A | #12 | #12 | 3/4" |
| 30-40A | #10 | #10 | 3/4" |
| 50A | #8 | #10 | 1" |
| 60-70A | #6 | #8 | 1" |
| 80-90A | #4 | #8 | 1.25" |
| 100A | #3 | #8 | 1.25" |
| 110-125A | #2 | #6 | 1.5" |
| 150A | #1 | #6 | 1.5" |
| 175A | #1/0 | #6 | 2" |
| 200A | #2/0 | #6 | 2" |
| 225A | #3/0 | #4 | 2" |
| 250A | #4/0 | #4 | 2.5" |
| 300A | 250 kcmil | #4 | 2.5" |
| 350A | 350 kcmil | #3 | 3" |
| 400A | 400 kcmil | #2 | 3" |
| 500A | 600 kcmil | #1 | 3.5" |
Values are based on standard NEC guidelines. Always verify with current electrical codes.