Electrical Cheat Sheet

Electrical Cheat Sheet


1. Ohm's Law

V = I × R


2. Power

P = V × I

P = I² × R

P = V² / R


3. Energy Consumption

E = P × t


4. Series Circuits

R_total = R1 + R2 + R3 + ...


5. Parallel Circuits

1/R_total = 1/R1 + 1/R2 + 1/R3 + ...


6. Voltage Division (Series)

Vx = (R_x / R_total) × V_total


7. Current Division (Parallel)

Ix = (R_total / R_x) × I_total


8. AC Formulas

V_RMS = V_peak / √2

I_RMS = I_peak / √2


9. Power Factor

PF = cos(ϕ) where ϕ is the phase angle


10. Reactance and Impedance

X_L = 2πfL (Inductive Reactance)

X_C = 1/(2πfC) (Capacitive Reactance)

Z = √(R² + (X_L - X_C)²)


Remember: Always check units and safety factors while designing circuits.

Power Design Guide

Initial Steps Before Low Voltage Power Design

Coordinate with state, local, and city ordinances

Either with outside consultant OR proceed with internal design

Initial Demand Load Estimating

Need SQ Estimates from Architectural Divisions before continuing

Review NFPA 70 - Article 230 for assistance

Load Estimating Reference

Load Type NFPA 70 Reference Notes
Receptacle Loads 220.14, 220.80 ~180VA for each receptacle
Lighting Loads 220.12, 220.80
HVAC Loads 220.61, 440
EV Charging 625
Equipment Loads 220.42
Outside Branch Circuits 225 Site Lighting (225.25), EMG/Fire Pumps (225.30 A)

Demand Load Calculator

Service Size Estimating

Ensure proper spare capacity has been accounted for - NFPA 70 Article 220.56

Standard Service Sizes

Common service sizes: 100A, 200A, 400A, 600A, 800A, 1000A, 1200A, 1600A, 2000A, 2500A, 3000A, 4000A

One-Line Programming

Key Considerations

  • Determine if service is greater or less than 1200A

    Typical cutoff for Switchboard vs. Distribution Main Panelboard

  • Determine Customer/Project metering requirements

    Ensure all loads are properly segregated and assigned metering

Panelboard Sizing Reference

Branch Load Type NFPA 70 Reference
HVAC Articles 440 and 220
Lighting Article 210
Receptacles Article 210
Emergency Articles 700 and 701

Panel Configuration

  • Determine if panels are to be MCB or MLO
  • Size MCB accordingly - NFPA 70 Article 240 (OCP)

Conductor Sizing

  • Consider AL or CU conductor type
  • Determine conductor sizing from estimated load
  • Determine estimated run length
  • Determine voltage drop and potential upsizing - NFPA 70 Article 220.55
  • Determine conduit size - NFPA 70 Annex C

    Must be below 30% fill rate

Microgrid Strategies

Strategy NFPA 70 Reference
BESS (Battery Energy Storage System) Article 706
On-Site Generation Article 705
External Microgrid Feed Paralleling Utility Article 705
Utility Back-Feed Article 702

Initial Power Layout - SD

Electrical Room Requirements

Requirement NFPA 70 Reference
Working clearances Article 110.26
Door/Exit requirements Article 314.20
Installation requirements Articles 300, 430
Disconnecting means requirements Article 225.30

Consider distance to sources of branch circuits when determining locations

Initial Layout Checklist

Overhead Doors, HVAC, Process Mechanical, Fire Smoke Dampeners, Actuators, Unit Heaters, Make Up Air Units, Condensing units, Pumps, etc.

Receptacle Placement Guidelines

  • Typically mounted at 18" afg - NFPA 70 Article 210.52(A)(1)
  • Typically no longer than 6' away from desired use/appliance - NFPA 70 Article 210.52(A)(1)
  • Determine receptacle use for tables/counters
  • Determine if space requires GFCI receptacles - NFPA 70 Article 210.8(B)
  • Determine if space requires floor box receptacle installations - NFPA 70 Article 210.52(A)(3)

Load Estimator

Project Information

Lighting Loads

General Lighting Load by Occupancy - NEC 2020 Table 220.12

Type of Occupancy Unit Load (VA/sq ft)
Office Buildings 1.30
Parking Garage 0.30
Transportation 1.20
Warehouses (storage) 1.25
Schools 3.00

Receptacle Loads

Typically 1.0 VA/sq ft for office spaces

HVAC & Major Equipment Loads

Summary of Demand Loads

Load Category Connected Load (kVA) Demand Factor (%) Demand Load (kVA)
Lighting 0.0 100 0.0
Receptacles 0.0 100 0.0
HVAC & Equipment 0.0 - 0.0
Total Demand Load 0.0 - 0.0

Ohm's Law Calculator

V = I × R | I = V / R | R = V / I

Power Calculator

Single Phase: P = V × I | Three Phase: P = √3 × V × I

HP Conversion

Conversion Factors:
• Mechanical HP: 1 HP = 745.7 W
• Electrical HP: 1 HP = 746.0 W
• Metric HP: 1 HP = 735.5 W

Voltage Drop Calculator

Wire Size Vd (V) % Vd

Pull/Handhole Box Sizing (Large)

Results

Small Junction Box Sizing

Results

Conductor Sizing/Ampacity Calculator

Internal Conductor Sizing

Standard Sizing Reference

Amp Range Phase Conductor Equip Ground Conduit
15-20A #12 #12 3/4"
30-40A #10 #10 3/4"
50A #8 #10 1"
60-70A #6 #8 1"
80-90A #4 #8 1.25"
100A #3 #8 1.25"
110-125A #2 #6 1.5"
150A #1 #6 1.5"
175A #1/0 #6 2"
200A #2/0 #6 2"
225A #3/0 #4 2"
250A #4/0 #4 2.5"
300A 250 kcmil #4 2.5"
350A 350 kcmil #3 3"
400A 400 kcmil #2 3"
500A 600 kcmil #1 3.5"

Values are based on standard NEC guidelines. Always verify with current electrical codes.